Commissioning of project namely Transmission System for evacuation of Power from REZ in Rajasthan (20 GW)…
As filed · Power Grid Corporation of India Limited has informed the Exchange about Commissioning of project namely Transmission System for evacuation of Power from REZ in Rajasthan (20 GW) under Phase-III Part-H
What happened
FactPower Grid Corporation of India has announced the commissioning of a project titled “Transmission System for evacuation of Power from REZ in Rajasthan (20 GW) under Phase-III Part-H.” This project was previously assigned to POWERGRID Beawar Dausa Transmission Limited, which has since amalgamated with POWERGRID Vataman Transmission Limited as of March 1, 2026, following an order from the Ministry of Corporate Affairs.
Why it matters
CapitSignal interpretationNew capacity spends capital now for volume later; the commissioning date is the commitment that can be checked against subsequent filings.
What management said before
Prior statements by this company that CapitSignal has recorded changing.
Capex
RevisedSo, we have ₹1,95,000 worth projects which are to be commissioned in next 3-4 years.
Last year, sorry, last meet, we have given ₹28,000 crores for FY26. We are increasing it to ₹32,000 crores as I told and for FY27, CapEx will be ₹37,000 crores. In FY28, it will be ₹45,000 crores.
Change
FactImplication
CapitSignal interpretationWatch next
Fact- Stated commissioning date
- Capital outlay and how it is funded
- Expected asset turns at full utilisation
- our capitalization for this financial year is going to be more than Rs 25,000 crores. (management committed by FY26)
- we have revised our Capex guideline to Rs. 32,000 crore. (management committed by FY26)
Evidence
- Power Grid Corporation of India Limited has informed the Exchange about Commissioning of project namely Transmission System for evacuation of Power from REZ in Rajasthan (20 GW) under Phase-III Part-H .(opens the original filing in a new tab)
- Earlier statement · Q3 FY25
- Latest statement · Q3 FY25
- Earlier statement · Q3 FY25
How CapitSignal classified this
- Reasoning:
- CAPACITY_EXPANSION base 54; +5 quantified amount; matched on subject
- Matched on:
- the filing's own subject line
- Confidence in the event type:
- 75%